All Free Civil Engineering MCQs with Answers

Every Civil Engineering question in the bank, across all chapters, each with the correct answer and a written explanation. Free and unlimited, with no account needed.

631 questions · page 5 of 32

  • A. To determine the sequence and timing of project activities
  • B. To calculate the contractor's final profit margin
  • C. To approve the architect's design drawings
  • D. To record the materials used after completion

Explanation: Scheduling identifies when activities start, finish, and interact with one another.

Correct answer: To determine the sequence and timing of project activities
  • A. Selecting the lowest tender submitted by contractors
  • B. Measuring work items from drawings and specifications
  • C. Checking defects after the building is occupied
  • D. Preparing the contractor's monthly payroll

Explanation: Quantity take-off measures the quantities of concrete, masonry, excavation, and other work items needed for the project.

Correct answer: Measuring work items from drawings and specifications
  • A. Audit charges for the contracting company
  • B. Site office rent for the contractor's head office
  • C. Concrete incorporated into the structural work
  • D. Interest on the contractor's general bank loan

Explanation: Concrete used in the specified work can be traced directly to that project, so it is a direct cost.

Correct answer: Concrete incorporated into the structural work
  • A. To record changes made after project completion
  • B. To establish the legal ownership of the project site
  • C. To decide the sequence of structural inspections
  • D. To determine the unit cost from resources and related charges

Explanation: Rate analysis builds a unit rate from materials, labour, equipment, overheads, and applicable profit.

Correct answer: To determine the unit cost from resources and related charges
  • A. An estimate predicts cost, while a tender is an offer to execute work at stated terms
  • B. An estimate is a signed contract, while a tender is a completed final account
  • C. An estimate records actual expenditure, while a tender measures completed quantities
  • D. An estimate approves variations, while a tender certifies monthly payments

Explanation: An estimate is prepared to forecast or assess the probable cost of proposed work.

Correct answer: An estimate predicts cost, while a tender is an offer to execute work at stated terms
  • A. To replace the construction drawings during site execution
  • B. To describe and quantify work items for pricing and payment
  • C. To certify that all materials meet laboratory standards
  • D. To act as the contractor's accident investigation report

Explanation: A bill of quantities lists measurable work items and their quantities, allowing comparable pricing and supporting valuation.

Correct answer: To describe and quantify work items for pricing and payment
  • A. Invitation to tender
  • B. Preliminary estimate
  • C. Final account
  • D. Site safety plan

Explanation: The final account settles the contract price after considering measured work, variations, claims, and other permitted adjustments.

Correct answer: Final account
  • A. The activity is removed from the construction programme
  • B. The activity automatically becomes a provisional sum
  • C. The contractor's indirect costs become direct material costs
  • D. The planned project completion date is likely to be delayed

Explanation: Critical path activities have no usable total float in the basic schedule, so a delay generally delays project completion.

Correct answer: The planned project completion date is likely to be delayed
  • A. Establishing procedures that prevent defects throughout the process
  • B. Repairing visible defects after the client rejects completed work
  • C. Measuring the quantity of excavation for interim payment
  • D. Comparing tender prices before awarding the contract

Explanation: Quality assurance is process-oriented and establishes systems, procedures, and controls intended to prevent defects.

Correct answer: Establishing procedures that prevent defects throughout the process
  • A. It guarantees that the contractor will receive the lowest tender price
  • B. It provides contemporaneous evidence for monitoring and contract administration
  • C. It replaces the need for a detailed construction programme
  • D. It converts all project costs into direct costs

Explanation: Daily site records support progress monitoring, resource control, valuation, and assessment of delays or claims.

Correct answer: It provides contemporaneous evidence for monitoring and contract administration
  • A. To reduce the number of contract clauses
  • B. To increase the tender markup automatically
  • C. To balance resource demand over the project period
  • D. To replace the approved construction drawings

Explanation: Resource leveling adjusts activity timing so labour, equipment, or other resources are not demanded beyond their available limits.

Correct answer: To balance resource demand over the project period
  • A. Concrete placed in a foundation
  • B. Bricks built into a wall
  • C. Steel reinforcement fixed in a slab
  • D. Site office administration expense

Explanation: Site office administration supports the project but is not incorporated into a specific measured work item.

Correct answer: Site office administration expense
  • A. To assess work completed for a progress payment
  • B. To calculate the contractor's final profit
  • C. To replace the original construction programme
  • D. To approve the contractor's permanent staff

Explanation: An interim valuation measures the value of work completed, materials properly brought to site, and approved adjustments for a payment…

Correct answer: To assess work completed for a progress payment
  • A. The client alone
  • B. The main contractor
  • C. The consulting quantity surveyor
  • D. The local building authority

Explanation: Under design and build, the main contractor accepts responsibility for coordinating and delivering both the design and the construction.

Correct answer: The main contractor
  • A. Increasing the number of site meetings
  • B. Issuing additional warning notices
  • C. Removing the hazard from the work process
  • D. Recording the hazard after an accident

Explanation: Eliminating the hazard is higher in the hierarchy of controls than warnings or personal protective equipment.

Correct answer: Removing the hazard from the work process
  • A. To determine the contractor's tax liability
  • B. To establish the final market value of the property
  • C. To certify the structural strength of completed work
  • D. To arrange temporary facilities and movement efficiently

Explanation: A site layout plan positions offices, storage areas, access routes, plant, welfare facilities, and safety zones for efficient operations.

Correct answer: To arrange temporary facilities and movement efficiently
  • A. For identified or possible uncertain costs
  • B. For the contractor's guaranteed personal income
  • C. For replacing all measured quantities
  • D. For paying only permanent site labour

Explanation: A contingency allowance provides for reasonable uncertainty, such as minor unforeseen work or cost variation, depending on the contract…

Correct answer: For identified or possible uncertain costs
  • A. To appoint the contractor's statutory auditor
  • B. To change the scope or details of the contracted work
  • C. To cancel every previous progress payment
  • D. To determine the weather conditions at the site

Explanation: A variation order formally authorizes an addition, omission, substitution, or change in the described work.

Correct answer: To change the scope or details of the contracted work
  • A. Contract duration with the soil bearing capacity
  • B. Site area with the building height
  • C. Actual cost with the approved or planned cost
  • D. Material colour with the approved finish

Explanation: Cost variance shows the difference between actual expenditure and a planned or approved cost baseline.

Correct answer: Actual cost with the approved or planned cost
  • A. It replaces the need for technical specifications
  • B. It prepares the contractor's income tax return
  • C. It selects the project financing institution
  • D. It verifies completed or ongoing work against requirements

Explanation: Quality control involves inspection, testing, and checking work and materials against drawings, specifications, and required standards.

Correct answer: It verifies completed or ongoing work against requirements