Which practice is most closely associated with quality assurance in construction?
Correct answer: A. Establishing procedures that prevent defects throughout the process
- A. Establishing procedures that prevent defects throughout the process
- B. Repairing visible defects after the client rejects completed work
- C. Measuring the quantity of excavation for interim payment
- D. Comparing tender prices before awarding the contract
Explanation
Quality assurance is process-oriented and establishes systems, procedures, and controls intended to prevent defects. Repairing defects is corrective quality control, while the other options concern measurement and procurement.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
A project activity lies on the critical path. What is the usual consequence of delaying it without mitigation?
Which document most directly records the agreed financial value of work after measured work and approved adjustments are finalized?
In a construction contract, what is the main function of a bill of quantities?
A contractor's site supervisor records labour, equipment, materials, weather, and daily progress. What is the main management value of this record?
What is the main purpose of resource leveling in a construction schedule?
Which item is normally classified as an indirect cost in a construction project?