A project activity lies on the critical path. What is the usual consequence of delaying it without mitigation?

Correct answer: D. The planned project completion date is likely to be delayed

  • A. The activity is removed from the construction programme
  • B. The activity automatically becomes a provisional sum
  • C. The contractor's indirect costs become direct material costs
  • D. The planned project completion date is likely to be delayed

Explanation

Critical path activities have no usable total float in the basic schedule, so a delay generally delays project completion. The other options describe unrelated contractual or costing actions.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions