A contractor's site supervisor records labour, equipment, materials, weather, and daily progress. What is the main management value of this record?
Correct answer: B. It provides contemporaneous evidence for monitoring and contract administration
- A. It guarantees that the contractor will receive the lowest tender price
- B. It provides contemporaneous evidence for monitoring and contract administration
- C. It replaces the need for a detailed construction programme
- D. It converts all project costs into direct costs
Explanation
Daily site records support progress monitoring, resource control, valuation, and assessment of delays or claims. They do not determine tender prices, replace scheduling, or change the classification of costs.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
Which practice is most closely associated with quality assurance in construction?
A project activity lies on the critical path. What is the usual consequence of delaying it without mitigation?
Which document most directly records the agreed financial value of work after measured work and approved adjustments are finalized?
What is the main purpose of resource leveling in a construction schedule?
Which item is normally classified as an indirect cost in a construction project?
What is the principal purpose of an interim valuation on a construction project?