Which activity is the primary purpose of construction project scheduling?
Correct answer: A. To determine the sequence and timing of project activities
- A. To determine the sequence and timing of project activities
- B. To calculate the contractor's final profit margin
- C. To approve the architect's design drawings
- D. To record the materials used after completion
Explanation
Scheduling identifies when activities start, finish, and interact with one another. Profit calculation, design approval, and final material records are separate management functions.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.