In a design and build procurement arrangement, who generally holds responsibility for both design and construction?
Correct answer: B. The main contractor
- A. The client alone
- B. The main contractor
- C. The consulting quantity surveyor
- D. The local building authority
Explanation
Under design and build, the main contractor accepts responsibility for coordinating and delivering both the design and the construction. The client still states requirements, while the authority mainly performs statutory functions.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
What is the principal purpose of an interim valuation on a construction project?
Which item is normally classified as an indirect cost in a construction project?
What is the main purpose of resource leveling in a construction schedule?
Which measure is most effective for controlling a hazard before relying on personal protective equipment?
What is the main function of a construction site layout plan?
How is a contingency allowance in an estimate generally intended to be used?