How is a contingency allowance in an estimate generally intended to be used?

Correct answer: A. For identified or possible uncertain costs

  • A. For identified or possible uncertain costs
  • B. For the contractor's guaranteed personal income
  • C. For replacing all measured quantities
  • D. For paying only permanent site labour

Explanation

A contingency allowance provides for reasonable uncertainty, such as minor unforeseen work or cost variation, depending on the contract and estimating practice. It is not a substitute for measuring the work or a guaranteed payment to the contractor.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions