All Free Civil Engineering MCQs with Answers
Every Civil Engineering question in the bank, across all chapters, each with the correct answer and a written explanation. Free and unlimited, with no account needed.
631 questions · page 6 of 32
101. What is the main purpose of a preliminary estimate prepared before detailed design is complete?
- A. To provide an early indication of probable project cost
- B. To determine the contractor's final payment
- C. To record the measured quantities of completed work
- D. To certify the quality of construction materials
Explanation: A preliminary estimate gives the client an approximate cost for feasibility and budget decisions when design information is incomplete.
Correct answer: To provide an early indication of probable project cost- A. Daily rainfall plotted against site temperature
- B. Cumulative cost or progress plotted against time
- C. Material density plotted against moisture content
- D. Labour strength plotted against floor area
Explanation: An S-curve shows cumulative project cost, expenditure, or physical progress against time.
Correct answer: Cumulative cost or progress plotted against time- A. The bidder submitting the highest price
- B. The first bidder delivering its documents
- C. The lowest evaluated responsive bidder
- D. The bidder with the shortest company name
Explanation: Public procurement commonly awards the work to the lowest evaluated bidder that meets the tender requirements and is responsive.
Correct answer: The lowest evaluated responsive bidder- A. To finance the client's unrelated projects
- B. To pay customs duties on imported equipment
- C. To replace the contractor's performance guarantee in every case
- D. To provide security for proper completion and defect correction
Explanation: Retention provides the client with financial security until the work is properly completed and relevant defects are corrected.
Correct answer: To provide security for proper completion and defect correction- A. A pre-agreed sum for specified delay or breach
- B. A bonus paid for using fewer materials
- C. A tax charged on the contractor's profit
- D. A provisional amount for design development
Explanation: Liquidated damages are an amount agreed in advance to compensate for a specified breach, commonly delay beyond the contractual completion…
Correct answer: A pre-agreed sum for specified delay or breach- A. The total contract value per project
- B. The output achieved per unit of labour input
- C. The number of drawings issued per consultant
- D. The percentage of overhead in a tender
Explanation: Labour productivity relates the quantity of work produced to the labour time or labour resources used.
Correct answer: The output achieved per unit of labour input- A. The amount of material wasted by the activity
- B. The cost reserved for unexpected site conditions
- C. The time the activity may slip without delaying project completion
- D. The number of workers assigned to the activity
Explanation: Total float is the time an activity can be delayed without delaying the planned project completion date, assuming other relationships…
Correct answer: The time the activity may slip without delaying project completion108. When using the centre-line method for estimating masonry quantities, what is a key requirement?
- A. The foundation depth is ignored in every case
- B. Every wall must have a different measured length
- C. Only the external plaster is measured
- D. The wall thicknesses and junction conditions must be handled consistently
Explanation: The centre-line method uses the total centre-line length of walls and must account correctly for junctions and changes in wall thickness.
Correct answer: The wall thicknesses and junction conditions must be handled consistently- A. To brief workers on task hazards and safe controls
- B. To approve the contractor's final account
- C. To calculate the concrete mix proportion
- D. To negotiate the tendering method with bidders
Explanation: A toolbox talk is a short site safety briefing focused on the hazards and controls for an intended activity.
Correct answer: To brief workers on task hazards and safe controls- A. A final record of all payments already made
- B. Work that was not included in the original sanctioned estimate
- C. A daily register of labour attendance
- D. A replacement for the contractor's tender security
Explanation: A supplementary estimate covers additional work or items not included in the original approved scope, subject to the applicable approval…
Correct answer: Work that was not included in the original sanctioned estimate- A. The employer, because payment follows actual quantities
- B. The consultant, because design review sets the price
- C. The contractor, because the agreed price is generally fixed
- D. The supplier, because material prices are guaranteed
Explanation: In a lump-sum contract, the contractor agrees to complete the defined work for a stated price.
Correct answer: The contractor, because the agreed price is generally fixed- A. Payment is based only on measured quantities
- B. Payment is determined by the lowest tendered amount
- C. Payment is made only after a fixed completion date
- D. Payment consists of cost plus an agreed fee or percentage
Explanation: A cost-plus contract reimburses the contractor for allowable project costs and adds an agreed fee or percentage for overhead and profit.
Correct answer: Payment consists of cost plus an agreed fee or percentage- A. To assess capability, experience, and financial capacity
- B. To determine the final quantity of concrete
- C. To replace the need for drawings and specifications
- D. To calculate the contractor's final account
Explanation: Prequalification screens firms for relevant experience, technical resources, financial strength, and past performance.
Correct answer: To assess capability, experience, and financial capacity- A. Awarding work without any price discussion
- B. Selecting a contractor and agreeing terms through direct negotiation
- C. Inviting every available contractor to submit sealed bids
- D. Using only the lowest rate in a standard schedule
Explanation: In a negotiated contract, the client discusses scope, price, and other terms directly with a selected contractor.
Correct answer: Selecting a contractor and agreeing terms through direct negotiation- A. To approve the architect's personal design changes
- B. To list only the contractor's office expenses
- C. To record measured quantities of completed work
- D. To replace the signed construction contract
Explanation: A measurement book records dimensions and quantities of work executed at the site.
Correct answer: To record measured quantities of completed work- A. Only wages paid to skilled workers
- B. Land value, taxes, rent, interest, and depreciation
- C. Only materials delivered to the site
- D. Materials, labour, equipment, overheads, and profit
Explanation: A complete unit rate commonly includes material, labour, equipment or tools, applicable overheads, and contractor profit.
Correct answer: Materials, labour, equipment, overheads, and profit- A. A reduction in value caused by age, wear, or obsolescence
- B. An increase caused by improved market demand
- C. The contractor's profit added to a measured item
- D. The temporary cost of mobilising site equipment
Explanation: Depreciation is the reduction in value of a building or asset due to physical deterioration, functional inadequacy, or economic…
Correct answer: A reduction in value caused by age, wear, or obsolescence- A. The ratio of planned value to contract duration
- B. The ratio of earned value to actual cost
- C. The difference between tender and final account
- D. The percentage of work delayed by weather
Explanation: The cost performance index is calculated as earned value divided by actual cost.
Correct answer: The ratio of earned value to actual cost- A. To certify the quality of delivered concrete
- B. To define the legal terms of a contract
- C. To display resource demand over time
- D. To calculate the depreciation of equipment
Explanation: A resource histogram displays the required amount of labour, equipment, or another resource during successive time periods.
Correct answer: To display resource demand over time- A. A final payment certificate
- B. A material delivery note
- C. A plant maintenance register
- D. A request for information
Explanation: A request for information, or RFI, formally asks the designer or responsible authority to clarify an unclear or conflicting requirement.
Correct answer: A request for information