All Free Civil Engineering MCQs with Answers

Every Civil Engineering question in the bank, across all chapters, each with the correct answer and a written explanation. Free and unlimited, with no account needed.

631 questions · page 6 of 32

  • A. To provide an early indication of probable project cost
  • B. To determine the contractor's final payment
  • C. To record the measured quantities of completed work
  • D. To certify the quality of construction materials

Explanation: A preliminary estimate gives the client an approximate cost for feasibility and budget decisions when design information is incomplete.

Correct answer: To provide an early indication of probable project cost
  • A. Daily rainfall plotted against site temperature
  • B. Cumulative cost or progress plotted against time
  • C. Material density plotted against moisture content
  • D. Labour strength plotted against floor area

Explanation: An S-curve shows cumulative project cost, expenditure, or physical progress against time.

Correct answer: Cumulative cost or progress plotted against time
  • A. The bidder submitting the highest price
  • B. The first bidder delivering its documents
  • C. The lowest evaluated responsive bidder
  • D. The bidder with the shortest company name

Explanation: Public procurement commonly awards the work to the lowest evaluated bidder that meets the tender requirements and is responsive.

Correct answer: The lowest evaluated responsive bidder
  • A. To finance the client's unrelated projects
  • B. To pay customs duties on imported equipment
  • C. To replace the contractor's performance guarantee in every case
  • D. To provide security for proper completion and defect correction

Explanation: Retention provides the client with financial security until the work is properly completed and relevant defects are corrected.

Correct answer: To provide security for proper completion and defect correction
  • A. A pre-agreed sum for specified delay or breach
  • B. A bonus paid for using fewer materials
  • C. A tax charged on the contractor's profit
  • D. A provisional amount for design development

Explanation: Liquidated damages are an amount agreed in advance to compensate for a specified breach, commonly delay beyond the contractual completion…

Correct answer: A pre-agreed sum for specified delay or breach
  • A. The total contract value per project
  • B. The output achieved per unit of labour input
  • C. The number of drawings issued per consultant
  • D. The percentage of overhead in a tender

Explanation: Labour productivity relates the quantity of work produced to the labour time or labour resources used.

Correct answer: The output achieved per unit of labour input
  • A. The amount of material wasted by the activity
  • B. The cost reserved for unexpected site conditions
  • C. The time the activity may slip without delaying project completion
  • D. The number of workers assigned to the activity

Explanation: Total float is the time an activity can be delayed without delaying the planned project completion date, assuming other relationships…

Correct answer: The time the activity may slip without delaying project completion
  • A. The foundation depth is ignored in every case
  • B. Every wall must have a different measured length
  • C. Only the external plaster is measured
  • D. The wall thicknesses and junction conditions must be handled consistently

Explanation: The centre-line method uses the total centre-line length of walls and must account correctly for junctions and changes in wall thickness.

Correct answer: The wall thicknesses and junction conditions must be handled consistently
  • A. To brief workers on task hazards and safe controls
  • B. To approve the contractor's final account
  • C. To calculate the concrete mix proportion
  • D. To negotiate the tendering method with bidders

Explanation: A toolbox talk is a short site safety briefing focused on the hazards and controls for an intended activity.

Correct answer: To brief workers on task hazards and safe controls
  • A. A final record of all payments already made
  • B. Work that was not included in the original sanctioned estimate
  • C. A daily register of labour attendance
  • D. A replacement for the contractor's tender security

Explanation: A supplementary estimate covers additional work or items not included in the original approved scope, subject to the applicable approval…

Correct answer: Work that was not included in the original sanctioned estimate
  • A. The employer, because payment follows actual quantities
  • B. The consultant, because design review sets the price
  • C. The contractor, because the agreed price is generally fixed
  • D. The supplier, because material prices are guaranteed

Explanation: In a lump-sum contract, the contractor agrees to complete the defined work for a stated price.

Correct answer: The contractor, because the agreed price is generally fixed
  • A. Payment is based only on measured quantities
  • B. Payment is determined by the lowest tendered amount
  • C. Payment is made only after a fixed completion date
  • D. Payment consists of cost plus an agreed fee or percentage

Explanation: A cost-plus contract reimburses the contractor for allowable project costs and adds an agreed fee or percentage for overhead and profit.

Correct answer: Payment consists of cost plus an agreed fee or percentage
  • A. To assess capability, experience, and financial capacity
  • B. To determine the final quantity of concrete
  • C. To replace the need for drawings and specifications
  • D. To calculate the contractor's final account

Explanation: Prequalification screens firms for relevant experience, technical resources, financial strength, and past performance.

Correct answer: To assess capability, experience, and financial capacity
  • A. Awarding work without any price discussion
  • B. Selecting a contractor and agreeing terms through direct negotiation
  • C. Inviting every available contractor to submit sealed bids
  • D. Using only the lowest rate in a standard schedule

Explanation: In a negotiated contract, the client discusses scope, price, and other terms directly with a selected contractor.

Correct answer: Selecting a contractor and agreeing terms through direct negotiation
  • A. To approve the architect's personal design changes
  • B. To list only the contractor's office expenses
  • C. To record measured quantities of completed work
  • D. To replace the signed construction contract

Explanation: A measurement book records dimensions and quantities of work executed at the site.

Correct answer: To record measured quantities of completed work
  • A. Only wages paid to skilled workers
  • B. Land value, taxes, rent, interest, and depreciation
  • C. Only materials delivered to the site
  • D. Materials, labour, equipment, overheads, and profit

Explanation: A complete unit rate commonly includes material, labour, equipment or tools, applicable overheads, and contractor profit.

Correct answer: Materials, labour, equipment, overheads, and profit
  • A. A reduction in value caused by age, wear, or obsolescence
  • B. An increase caused by improved market demand
  • C. The contractor's profit added to a measured item
  • D. The temporary cost of mobilising site equipment

Explanation: Depreciation is the reduction in value of a building or asset due to physical deterioration, functional inadequacy, or economic…

Correct answer: A reduction in value caused by age, wear, or obsolescence
  • A. The ratio of planned value to contract duration
  • B. The ratio of earned value to actual cost
  • C. The difference between tender and final account
  • D. The percentage of work delayed by weather

Explanation: The cost performance index is calculated as earned value divided by actual cost.

Correct answer: The ratio of earned value to actual cost
  • A. To certify the quality of delivered concrete
  • B. To define the legal terms of a contract
  • C. To display resource demand over time
  • D. To calculate the depreciation of equipment

Explanation: A resource histogram displays the required amount of labour, equipment, or another resource during successive time periods.

Correct answer: To display resource demand over time
  • A. A final payment certificate
  • B. A material delivery note
  • C. A plant maintenance register
  • D. A request for information

Explanation: A request for information, or RFI, formally asks the designer or responsible authority to clarify an unclear or conflicting requirement.

Correct answer: A request for information