Which document is commonly used to obtain formal clarification about an ambiguity in construction drawings or specifications?

Correct answer: D. A request for information

  • A. A final payment certificate
  • B. A material delivery note
  • C. A plant maintenance register
  • D. A request for information

Explanation

A request for information, or RFI, formally asks the designer or responsible authority to clarify an unclear or conflicting requirement. The response creates a documented basis for carrying out the affected work.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions