In earned value analysis, what does the cost performance index primarily indicate?
Correct answer: B. The ratio of earned value to actual cost
- A. The ratio of planned value to contract duration
- B. The ratio of earned value to actual cost
- C. The difference between tender and final account
- D. The percentage of work delayed by weather
Explanation
The cost performance index is calculated as earned value divided by actual cost. A value above one indicates that the work accomplished has cost less than the budgeted value of that work, while a value below one indicates cost inefficiency.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
In property valuation for construction purposes, what does depreciation generally represent?
In a unit rate estimate, which combination most appropriately forms the basic rate of a construction item?
What is the usual purpose of a measurement book maintained on a public works project?
What is the main use of a resource histogram in construction planning?
Which document is commonly used to obtain formal clarification about an ambiguity in construction drawings or specifications?
What is the main purpose of a work breakdown structure in construction management?