In construction estimating, what does labour productivity usually express?
Correct answer: B. The output achieved per unit of labour input
- A. The total contract value per project
- B. The output achieved per unit of labour input
- C. The number of drawings issued per consultant
- D. The percentage of overhead in a tender
Explanation
Labour productivity relates the quantity of work produced to the labour time or labour resources used. It is useful in estimating activity durations, labour costs, and resource requirements.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
What do liquidated damages in a construction contract generally represent?
What is the usual purpose of retention money deducted from a contractor's interim payments?
Under open competitive tendering, which bidder is normally selected for award?
In a project network, what does total float of an activity indicate?
When using the centre-line method for estimating masonry quantities, what is a key requirement?
What is the main purpose of a toolbox talk held before a site task begins?