When using the centre-line method for estimating masonry quantities, what is a key requirement?

Correct answer: D. The wall thicknesses and junction conditions must be handled consistently

  • A. The foundation depth is ignored in every case
  • B. Every wall must have a different measured length
  • C. Only the external plaster is measured
  • D. The wall thicknesses and junction conditions must be handled consistently

Explanation

The centre-line method uses the total centre-line length of walls and must account correctly for junctions and changes in wall thickness. Inconsistent treatment at intersections can cause overmeasurement or undermismeasurement.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions