Free Time and Work MCQs with Answers
120 Time and Work MCQs from Mathematics, each with the correct answer and a written explanation of why it is correct. Free and unlimited, with no account needed.
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Last updated
120 questions · page 2 of 6
- A. 5 days
- B. 10 days
- C. 15 days
- D. 12 days
Explanation: P's rate is 1/20 of the work per day and Q's rate is 1/12 of the work per day. P works alone for 4 days and completes 4/20 = 1/5, leaving 4/5; together their rate is 1/20 + 1/12 = 2/15 per day, so the remaining work takes (4/5) ÷ (2/15 per day) = 6 days, making 4 days + 6 days = 10 days. Students may choose 12 days by adding the individual completion times instead of combining their rates.
Correct answer: 10 days- A. 8
- B. 6
- C. 4
- D. 2
Explanation: Q completes 10 days x 1/15 of the work per day = 2/3 of the work, leaving 1/3. P works at 1/18 of the work per day, so the remaining time is (1/3) ÷ (1/18 per day) = 6 days. Students may choose 4 days by using Q's faster rate for P's remaining work.
Correct answer: 6- A. 9(3/5) days
- B. 9(1/5) days
- C. 9(2/5) days
- D. 10 days
Explanation: P, Q and R together work at 1/4 of the track per day, while P and Q together work at 1/16 + 1/12 = 7/48 of the track per day. Thus R's rate is 1/4 - 7/48 = 5/48 of the work per day, so R alone needs 1 ÷ (5/48 per day) = 48/5 days = 9 3/5 days. Students may choose 9 2/5 days by making an arithmetic error when subtracting the rates.
Correct answer: 9(3/5) days- A. 12 hrs
- B. 14 hrs
- C. 16 hrs
- D. 18 hrs
Explanation: The combined filling rate of X and Y is 1/15 + 1/20 = 7/60 of the tank per hour, and Z empties 1/25 of the tank per hour, giving an initial net rate of 23/300 of the tank per hour. In 10 hours they fill 10 x 23/300 = 23/30 of the tank, leaving 7/30; after Z closes, the remaining time is (7/30) ÷ (7/60 per hour) = 2 hours, so the total time is 10 hours + 2 hours = 12 hours. Students may choose 14 hours by adding 2 hours to the wrong stage or treating Z as open throughout.
Correct answer: 12 hrs- A. 12 days
- B. 16 days
- C. 18 days
- D. 20 days
Explanation: If 1 man works 1.5 times as much as 1 boy, then 1 boy equals 2/3 of a man's daily work. The required work is 8 men x 20 days = 160 man-days, while 4 men + 9 boys have daily capacity 4 + 9 x 2/3 = 10 man-equivalents, so the time is 160 man-days ÷ 10 man-equivalents per day = 16 days. Students may choose 18 days by treating 9 boys as 6 men incorrectly or rounding the conversion.
Correct answer: 16 days- A. 85 days
- B. 126 days
- C. 118 days
- D. 136 days
Explanation: Efficiency and time are inversely proportional, so Rashid's and Danish's times are in the ratio 8:5 when their efficiencies are 5:8. Let their times be 8x days and 5x days; their difference is 3x days = 51 days, giving x = 17 days and Rashid's time = 8 x 17 days = 136 days. Students may choose 85 days by applying the efficiency ratio directly to time instead of inversely.
Correct answer: 136 days- A. 16
- B. 4
- C. 12
- D. 8
Explanation: The total work is 12 men x 8 hours per day x 10 days = 960 man-hours. At 12 hours per day for 5 days, each man supplies 60 hours, so the required number is 960 man-hours ÷ 60 hours per man = 16 men. Students may choose 12 men by comparing only the number of days and ignoring the change in daily working hours.
Correct answer: 16- A. 15
- B. 14
- C. 16
- D. 13
Explanation: Forty women working for 30 days provide 40 x 30 = 1,200 woman-days, so a woman's wage is Rs.21,600 ÷ 1,200 woman-days = Rs.18 per day. A man's wage is double, Rs.36 per day, hence one man earns 25 days x Rs.36 per day = Rs.900 and the required number is Rs.14,400 ÷ Rs.900 per man = 16 men. Students may choose 15 men by rounding the daily wage or forgetting that the man's wage is double the woman's.
Correct answer: 16- A. 7 hour 15 minutes
- B. 7 hour 30 minutes
- C. 8 hour 15 minutes
- D. 8 hour 30 minutes
Explanation: Mansoor types 32 pages ÷ 6 hours = 16/3 pages per hour, while Aaqib types 40 pages ÷ 5 hours = 8 pages per hour. Together their rate is 16/3 + 8 = 40/3 pages per hour, so 110 pages take 110 pages ÷ (40/3 pages per hour) = 8.25 hours = 8 hours 15 minutes. Students may choose 8 hours 30 minutes by rounding 8.25 hours instead of converting the quarter hour exactly.
Correct answer: 8 hour 15 minutes- A. 3 pm
- B. 2 pm
- C. 1:00 pm
- D. 11 am
Explanation: In the first 2 hours, the three machines print 2 x (1/8 + 1/10 + 1/12) = 2 x 37/120 = 37/60 of the job. The remaining 23/60 is printed by Q and R at 1/10 + 1/12 = 11/60 job per hour, taking (23/60) ÷ (11/60 per hour) = 23/11 hours, about 2 hours 5 minutes; starting at 11:00 am, completion is about 1:05 pm, approximately 1:00 pm. Students may choose 2:00 pm by rounding the remaining time up to 3 hours.
Correct answer: 1:00 pm- A. 8/15
- B. 7/15
- C. 11/15
- D. 2/11
Explanation: Their combined rate is 1/15 + 1/20 = 7/60 of the work per day. In 4 days they complete 4 x 7/60 = 7/15 of the work, so the fraction left is 1 - 7/15 = 8/15. Students may choose 7/15 by reporting the fraction completed rather than the fraction remaining.
Correct answer: 8/15- A. 40 days
- B. 50 days
- C. 60 days
- D. 70 days
Explanation: A and B together complete 1/15 of the work per day, while B alone completes 1/20 per day. Therefore A's rate is 1/15 - 1/20 = 1/60 of the work per day, so A alone needs 60 days. Students may choose 40 days by subtracting the completion times, 20 days - 15 days, instead of subtracting the work rates.
Correct answer: 60 days- A. 50
- B. 75
- C. 60
- D. 45
Explanation: Together they complete 20 days x 1/30 of the work per day = 2/3, leaving 1/3 for Kashif. Kashif's rate is (1/3) ÷ 25 days = 1/75 of the work per day, so Farjan's rate is 1/30 - 1/75 = 1/50 of the work per day and Farjan alone needs 50 days. Students may choose 75 days by taking Kashif's individual time as Farjan's time.
Correct answer: 50- A. 12:00 pm
- B. 2:00 am
- C. 12:00 am
- D. 10:00 pm
Explanation: Jameel works from 9:00 am to 2:00 pm, which is 5 hours, and completes 5 hours x 1/15 of the work per hour = 1/3 of the work. Nasir completes the remaining 2/3 at 1/12 of the work per hour, requiring 8 hours; beginning at 4:00 pm, the task finishes at 12:00 am. Students may choose 2:00 am by mistakenly counting the 2-hour gap as working time or using a 10-hour completion period.
Correct answer: 12:00 am- A. 10
- B. 9
- C. 11
- D. 12
Explanation: Q and R together work at 1/9 + 1/12 = 7/36 of the task per day, so in 3 days they complete 3 x 7/36 = 7/12, leaving 5/12. P works at 1/24 of the task per day, hence the remaining time is (5/12) ÷ (1/24 per day) = 10 days. Students may choose 9 days by subtracting the three-day start from the incorrect assumption that Q and R complete the whole task in 12 days.
Correct answer: 10- A. 14
- B. 16
- C. 15
- D. 11
Explanation: Kamal's rate is 1/20 of the work per day. Suresh is 25% more efficient, so his rate is 1.25 x 1/20 = 1/16 work per day, meaning he needs 16 days. The likely mistake is choosing 15 days, treating 25% more efficiency as 5 fewer days rather than increasing the work rate.
Correct answer: 16- A. 37 ½ days
- B. 22 days
- C. 31 days
- D. 22 days
Explanation: A completes 80% in 20 days, so A's rate is 0.8/20 = 0.04 = 1/25 work per day. Together they complete 20% in 3 days, giving a combined rate of 0.2/3 = 1/15, so B's rate is 1/15 - 1/25 = 2/75 and B alone needs 75/2 = 37.5 days. The likely mistake is 22 days, which does not follow from subtracting the two work rates correctly.
Correct answer: 37 ½ days- A. 75/8 days
- B. 44/6 days
- C. 48/5 days
- D. None of these
Explanation: A's rate is (1/3) / 5 = 1/15 work per day, and B's rate is (2/5) / 10 = 1/25 work per day. Their combined rate is 1/15 + 1/25 = 8/75, so the required time is 1 / (8/75) = 75/8 days. The likely mistake is 48/5 days, which results from combining the given fractions without converting them into daily rates.
Correct answer: 75/8 days- A. 12
- B. 8
- C. 10
- D. 9
Explanation: The combined rate equation is 1/X + 1/(X+5) = 1/6. Multiplying through gives 6(2X+5) = X(X+5), so X² - 7X - 30 = 0 = (X-10)(X+3), and the positive value is X = 10 days. The likely mistake is 8 days, which does not satisfy the combined-rate equation.
Correct answer: 10- A. 7
- B. 8
- C. 9
- D. 10
Explanation: The rates of P+Q, Q+R, and P+Q+R are 1/8, 1/12, and 1/6 work per day. Q's rate is 1/8 + 1/12 - 1/6 = 1/24, so P+R's rate is 1/6 - 1/24 = 1/8. Therefore P and R need 8 days together. The likely mistake is 9 days, which comes from combining the pair times directly instead of their rates.
Correct answer: 8