Jameel can complete a task in 15 hours and Nasir can complete the same task in 12 hours. Jameel starts the task at 9:00 am and stops working at 2:00pm. Nasir starts working on the task at 4:00 pm. At what time is the task completed?
Correct answer: C. 12:00 am
- A. 12:00 pm
- B. 2:00 am
- C. 12:00 am
- D. 10:00 pm
Explanation
Jameel works from 9:00 am to 2:00 pm, which is 5 hours, and completes 5 hours x 1/15 of the work per hour = 1/3 of the work. Nasir completes the remaining 2/3 at 1/12 of the work per hour, requiring 8 hours; beginning at 4:00 pm, the task finishes at 12:00 am. Students may choose 2:00 am by mistakenly counting the 2-hour gap as working time or using a 10-hour completion period.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
About Time and Work
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Practise Arithmetic
1,060 free Arithmetic MCQs from Mathematics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Mathematics questions like this
Mathematics is on 76 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Time and Work questions
Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
A and B can together do a piece of work in 15 days. B alone can do it in 20 days. In how many days can A alone do it ?
P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in_________days.
Kamal will complete work in 20 days. If Suresh is 25% more efficient than Kamal, he can complete the work in________days.
A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?