Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Last updated
120 questions · page 1 of 6
1. A can complete a job in 10 days and B in 15 days. Working together, how many days will they take?
- A. 5 days
- B. 6 days
- C. 8 days
- D. 12 days
Explanation: Work with rates, not days. A does 1/10 of the job per day and B does 1/15. Together they do 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6 per day, so the job takes 6 days.
Correct answer: 6 days- A. 45 hours
- B. 47 hours
- C. 48 hours
- D. 50 hours
Explanation: The basic hourly rate is Rs. 20 / 40 hours = Rs. 0.50 per hour, so the overtime rate is Rs. 0.50 x 1.25 = Rs. 0.625 per hour. The overtime earning is Rs. 25 - Rs. 20 = Rs. 5, requiring Rs. 5 / Rs. 0.625 = 8 overtime hours, hence 40 + 8 = 48 hours. Students often choose option a by treating the extra Rs. 5 as payment for only 5 hours at the basic rate and ignoring the 25% overtime premium.
Correct answer: 48 hours- A. 12
- B. 15
- C. 22
- D. 20
Explanation: P's rate is 1/15 job per day and Q's rate is 1/10 job per day. In 2 days they complete 2/15 + 2/10 = 1/3 of the job, leaving 2/3; P takes (2/3) / (1/15) = 10 days, so total time is 2 days + 10 days = 12 days. The likely mistake is option b, 15 days, from ignoring the work completed by Q before he left.
Correct answer: 12- A. 70
- B. 50
- C. 40
- D. 60
Explanation: Together, A and B complete 20 days x 1/30 job per day = 2/3 of the job in 20 days. A alone completes the remaining 1/3 in 20 days, so A's rate is (1/3) / 20 days = 1/60 job per day, meaning A alone needs 60 days. The likely mistake is option c, 40 days, from treating the remaining one-third as if A completed one-half of the work.
Correct answer: 60- A. 18 days
- B. 22 ½ days
- C. 24 days
- D. 26 days
Explanation: If B's rate is r jobs per day, A's rate is 3r jobs per day, so their times are 1/r days and 1/(3r) days. Their time difference is 1/r - 1/(3r) = 60 days, giving 2/(3r) = 60 days and r = 1/90 job per day. Together their rate is 4/90 job per day, so time = 90/4 days = 22.5 days. The likely mistake is option c, 24 days, from rounding or not applying the three-times rate correctly.
Correct answer: 22 ½ days- A. 3 hrs.
- B. 4 hrs,
- C. 5 hrs.
- D. 6 hrs.Education
Explanation: Tap X fills 1/10 tank per hour and tap Y fills 1/15 tank per hour. Together their rate is 1/10 + 1/15 = 1/6 tank per hour, so the filling time is 6 hours. The likely mistake is option c, 5 hours, from adding the filling times instead of adding the rates.
Correct answer: 6 hrs.Education- A. 12 days
- B. 14 days
- C. 16 days
- D. 18 days
Explanation: Since 3 men and 4 women do the same work in 43 days, 4 women have the work rate of 3 men, so one woman equals 3/4 of a man's rate. The rate of 7 men and 5 women is 7 + 5 x 3/4 = 43/4 man-units per day, while the work is 3 x 43 = 129 man-days; time = 129 / (43/4) = 12 days. The likely mistake is option b, 14 days, from treating a woman as equal to a man.
Correct answer: 12 days- A. 1.8 days
- B. 1.5 days
- C. 1.2 days
- D. 1 day
Explanation: Six men working for 2 days provide 6 x 2 = 12 man-days to make 10 sofas, so each sofa requires 12/10 = 1.2 man-days. For 8 sofas, the required work is 8 x 1.2 = 9.6 man-days; 8 men therefore take 9.6/8 = 1.2 days. The likely mistake is option b, 1.5 days, from scaling the number of men or sofas in the wrong direction.
Correct answer: 1.2 days- A. 1
- B. 5
- C. 10
- D. 25
Explanation: The original task uses 10 workers x 10 days = 100 worker-days to make 10 tables, so each table requires 10 worker-days. Five tables require 5 x 10 = 50 worker-days, and 5 workers complete them in 50/5 = 10 days. The likely mistake is option b, 5 days, from reducing both workers and tables but forgetting that the worker-to-table ratio remains unchanged.
Correct answer: 10- A. 2 men
- B. 12 men
- C. 9 men
- D. 18 men
Explanation: The total work is 6 men x 9 days = 54 man-days. To finish the same 54 man-days in 3 days requires 54/3 = 18 men. The likely mistake is option c, 9 men, from dividing the number of men by the time ratio instead of multiplying it by 9 days / 3 days.
Correct answer: 18 men- A. Rs.1104
- B. Rs.1000
- C. Rs.934
- D. Rs.1210
Explanation: Let one goat's daily cost be g rupees, so one cow's daily cost is 5g rupees. The given cost gives (20 x 5g + 40g) x 10 days = Rs.460, so 1400g = Rs.460 and g = Rs.23/70 per day. The new cost is (50 x 5g + 30g) x 12 days = 3360g = 3360 x Rs.23/70 = Rs.1104. The likely mistake is option d, Rs.1210, from failing to apply the 12-day duration or the five-goats-to-one-cow cost relation.
Correct answer: Rs.1104- A. 50
- B. 30
- C. 40
- D. 13
Explanation: Let a man's rate be m jobs per day and a woman's rate be w jobs per day. The statements give 3m + 7w = 1/10 job per day and 4m + 6w = 1/8 job per day; solving gives w = 1/400 job per day. Ten women work at 10/400 = 1/40 job per day, so they need 40 days. The likely mistake is option d, 13 days, from averaging the two given completion times instead of solving the worker-rate equations.
Correct answer: 40- A. 10 days
- B. 14 days
- C. 15 days
- D. 9 days
Explanation: P's rate is 1/20 job per day, while Q and R add 1/30 + 1/60 = 1/20 job per day on every third day. In each 3-day cycle, the work is 1/20 + 1/20 + (1/20 + 1/30 + 1/60) = 1/5 job, so 5 cycles complete the job in 5 x 3 days = 15 days. The likely mistake is option a, 10 days, from assuming Q and R assist every day rather than only on every third day.
Correct answer: 15 days- A. 10 min
- B. 20 min
- C. 30 min
- D. 40 min
Explanation: For the first 10 minutes, the two pipes fill 10 x (1/20 + 1/60) = 10/15 = 2/3 of the tank. The remaining 1/3 is filled by the second pipe at 1/60 tank per minute, requiring (1/3) / (1/60) = 20 minutes. The likely mistake is option c, 30 minutes, from using the combined rate after the first pipe has been shut.
Correct answer: 20 min- A. 15 days
- B. 14 days
- C. 16 days
- D. 30 days
Explanation: A is three times as efficient as B, so A's time is one-third of B's time. If B takes t days, then t - t/3 = 10 days, giving 2t/3 = 10 days and t = 15 days. The likely mistake is option d, 30 days, from interpreting 'thrice as good' as a difference of three times rather than a rate ratio of 3:1.
Correct answer: 15 days- A. 6 days
- B. 8 days
- C. 10 days
- D. 12 days
Explanation: If one man's rate is m jobs per day, each child's rate is m/2 jobs per day because a child takes twice as long. Thus 8 children and 12 men have rate 8 x m/2 + 12m = 16m jobs per day, completing 16m x 9 days = 144m of work. Twelve men work at 12m jobs per day, so the time is 144m/12m = 12 days. The likely mistake is option a, 6 days, from treating each child as equal to a man instead of half as productive.
Correct answer: 12 days17. 15 men can build a 500m long wall in 30 days. In how many days can 30 men build a 1.2 km long wall?
- A. 48 days
- B. 24 days
- C. 40 days
- D. 36 days
Explanation: The work is proportional to wall length and the number of man-days. For 500 m, the work is 15 men x 30 days = 450 man-days, so for 1,200 m, required work is 450 x 1,200/500 = 1,080 man-days; 1,080 man-days ÷ 30 men = 36 days. Students may choose 48 days by adjusting the wall length but forgetting that the number of men also doubles.
Correct answer: 36 days- A. 24 days
- B. 14 days
- C. 15 days
- D. 20 days
Explanation: The total work is 28 men x 15 days = 420 man-days. Therefore, 21 men need 420 man-days ÷ 21 men = 20 days. Students may choose 24 days by using an incorrect inverse proportion calculation.
Correct answer: 20 days- A. 10 days
- B. 12 days
- C. 8 days
- D. 9 days
Explanation: C completes half the work in 6 days, so C's rate is 1/12 of the work per day; in 4 days C completes 4/12 = 1/3 of the work, leaving 2/3. D completes 1/3 in 5 days, so D's rate is 1/15 of the work per day, and the remaining work takes (2/3) ÷ (1/15 per day) = 10 days. Students may choose 12 days by treating D's rate as 1/18 of the work per day.
Correct answer: 10 days- A. Rs.40
- B. Rs.70
- C. Rs.90
- D. Rs.100
Explanation: Let the daily earnings of P, Q and R be p, q and r rupees per day. From the data, p + q + r = Rs.1620 ÷ 9 days = Rs.180 per day, p + r = Rs.600 ÷ 5 days = Rs.120 per day, and q + r = Rs.910 ÷ 7 days = Rs.130 per day; subtracting gives q = Rs.60 per day and then r = Rs.70 per day. Students may choose Rs.90 by subtracting the combined amounts without first converting them to daily earnings.
Correct answer: Rs.70Time and Work MCQs: common questions
Are these Time and Work MCQs free?
Yes. All Time and Work MCQs from Mathematics are free on TestUstad, with unlimited attempts and no account needed. Nothing on this page is a sample or a trial.
How many Time and Work MCQs are on this page?
There are 120 Time and Work MCQs in the Mathematics bank, shown 20 to a page with the correct answer and an explanation on each.
Does every Time and Work MCQ have an explanation?
Yes. Each Time and Work question shows the correct option and a written explanation of why it is correct, so a wrong answer teaches you something rather than just being marked wrong.
Can I take a timed Time and Work test?
Yes. The practice button on this page starts a free Time and Work test drawn from the Mathematics bank. It marks each answer instantly, gives you a score at the end, and can be retaken as many times as you like.