A is thrice as good as B in work. A is able to finish a job in 60 days less than B. They can finish the work in___________days if they work together.
Correct answer: B. 22 ½ days
- A. 18 days
- B. 22 ½ days
- C. 24 days
- D. 26 days
Explanation
If B's rate is r jobs per day, A's rate is 3r jobs per day, so their times are 1/r days and 1/(3r) days. Their time difference is 1/r - 1/(3r) = 60 days, giving 2/(3r) = 60 days and r = 1/90 job per day. Together their rate is 4/90 job per day, so time = 90/4 days = 22.5 days. The likely mistake is option c, 24 days, from rounding or not applying the three-times rate correctly.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
About Time and Work
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Practise Arithmetic
1,060 free Arithmetic MCQs from Mathematics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Mathematics questions like this
Mathematics is on 76 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Time and Work questions
A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in__________days.
A man's basic pay for a 40 hour week is Rs. 20 overtime is paid for at 25 % above the basic rate, in a certain week he worked overtime and his total wage was Rs. 25. He therefore worked for a total of:________?
Two taps X and Y can fill a tank in 10 hrs. and 15 hrs.respectively. If the both taps are opened together, the tank will be full in_________?
If 3 men or 4 women can construct a wall in 43 days, then the number of days that 7 men and 5 women take to construct it is :
If 6 men can make 10 sofas in 2 days, then 8 men can make 8 sofas in__________?