If 6 men take 9 days to complete a work, how many men can complete the work in 3 days?
Correct answer: D. 18 men
- A. 2 men
- B. 12 men
- C. 9 men
- D. 18 men
Explanation
The total work is 6 men x 9 days = 54 man-days. To finish the same 54 man-days in 3 days requires 54/3 = 18 men. The likely mistake is option c, 9 men, from dividing the number of men by the time ratio instead of multiplying it by 9 days / 3 days.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
About Time and Work
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Practise Arithmetic
1,060 free Arithmetic MCQs from Mathematics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Mathematics questions like this
Mathematics is on 76 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Time and Work questions
If 10 workers can make 10 tables in 10 days, then how many days would it take for 5 workers to make 5 tables?
If 6 men can make 10 sofas in 2 days, then 8 men can make 8 sofas in__________?
If 3 men or 4 women can construct a wall in 43 days, then the number of days that 7 men and 5 women take to construct it is :
Assume that 20 cows and 40 goats can be kept for 10 days for Rs.460. If the cost of keeping 5 goats is the same as the cost of keeping 1 cow, what will be the cost for keeping 50 cows and 30 goats for 12 days?
3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the work and he is assisted by Q and R on every third day?