A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 10 days. In how many days both A and B together can do the work ?
Correct answer: A. 75/8 days
- A. 75/8 days
- B. 44/6 days
- C. 48/5 days
- D. None of these
Explanation
A's rate is (1/3) / 5 = 1/15 work per day, and B's rate is (2/5) / 10 = 1/25 work per day. Their combined rate is 1/15 + 1/25 = 8/75, so the required time is 1 / (8/75) = 75/8 days. The likely mistake is 48/5 days, which results from combining the given fractions without converting them into daily rates.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
About Time and Work
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Practise Arithmetic
1,060 free Arithmetic MCQs from Mathematics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Mathematics questions like this
Mathematics is on 76 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Time and Work questions
A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?
Kamal will complete work in 20 days. If Suresh is 25% more efficient than Kamal, he can complete the work in________days.
P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in_________days.
A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it?
P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in__________?