All Free Mathematics MCQs with Answers

Every Mathematics question in the bank, across all chapters, each with the correct answer and a written explanation. Free and unlimited, with no account needed.

1,551 questions · page 61 of 78

  • A. 12
  • B. 8
  • C. 10
  • D. 9

Explanation: The combined rate equation is 1/X + 1/(X+5) = 1/6. Multiplying through gives 6(2X+5) = X(X+5), so X² - 7X - 30 = 0 = (X-10)(X+3), and the…

Correct answer: 10
  • A. 7
  • B. 8
  • C. 9
  • D. 10

Explanation: The rates of P+Q, Q+R, and P+Q+R are 1/8, 1/12, and 1/6 work per day. Q's rate is 1/8 + 1/12 - 1/6 = 1/24, so P+R's rate is 1/6 - 1/24 =…

Correct answer: 8
  • A. 30 days
  • B. 25 days
  • C. 20 days
  • D. 15 days

Explanation: Let Q's rate be q and R's rate be 1/50. Since P can do the work in the same time as Q and R together, P's rate is q + 1/50.

Correct answer: 25 days
  • A. 5,750 litres
  • B. 5,760 litres
  • C. 6,890 litres
  • D. None of these

Explanation: Let the tank capacity be V litres. The leak removes V/6 litres per hour, while the inlet supplies 4 litres per minute = 240 litres per…

Correct answer: 5,760 litres
  • A. 12 min
  • B. 14 min
  • C. 16 min
  • D. 20 min

Explanation: The filling rate is 1/32 tank per minute and the emptying rate is 1/16 tank per minute, so the net rate is 1/32 - 2/32 = -1/32 tank per…

Correct answer: 16 min
  • A. 20 days
  • B. 30 days
  • C. 40 days
  • D. none of these

Explanation: The pair rates are A+B = 1/12, B+C = 1/15, and C+A = 1/20. Adding them gives 2(A+B+C) = 1/12 + 1/15 + 1/20 = 1/5, so the total rate is…

Correct answer: 30 days
  • A. 2
  • B. 8
  • C. 10
  • D. 12

Explanation: The original labour is 10 bulls x 3 days x 10 hours = 300 bull-hours for 20 fields, or 15 bull-hours per field.

Correct answer: 2
  • A. 2
  • B. 3 3⁄7
  • C. 4 ¼
  • D. 5Election Officer Mcqs

Explanation: Their combined daily rate is 1/24 + 1/6 + 1/12 = 1/24 + 4/24 + 2/24 = 7/24 work per day.

Correct answer: 3 3⁄7
  • A. 2 min
  • B. 3 min
  • C. 4 min
  • D. 5 min

Explanation: If Q is closed after t minutes, P works for all 9 minutes and Q works for t minutes.

Correct answer: 4 min
  • A. 12/6 days
  • B. 15/2 days
  • C. 23 days
  • D. 34 days

Explanation: A's rate is 1/12 work per day. B is 60% more efficient, so B's rate is 1.6 x 1/12 = 1/7.5 work per day, and B's time is 12/1.6 = 7.5 days…

Correct answer: 15/2 days
  • A. 70 days
  • B. 120/7 days
  • C. 50 days
  • D. 45 days

Explanation: A's rate is 1/30 work per day and B's rate is 1/40 work per day, so together their rate is 1/30 + 1/40 = 7/120 work per day.

Correct answer: 120/7 days
  • A. 20
  • B. 25
  • C. 125
  • D. 60

Explanation: The number of tasks is proportional to the number of men and working hours, so tasks = 50 × (10 men × 6 hours) ÷ (6 men × 4 hours) = 125…

Correct answer: 125
  • A. 1
  • B. 2
  • C. 3
  • D. 4

Explanation: Q's rate is 1/12 work per day, and P works twice as fast, so P's rate is 2/12 = 1/6 work per day.

Correct answer: 4
  • A. 9
  • B. 11
  • C. 23
  • D. 13

Explanation: P's rate is 1/23 work per day; since P is 30% more efficient, Q's rate is 1/1.3 of P's rate = 10/299 work per day.

Correct answer: 13
  • A. 4 days
  • B. 6 days
  • C. 2 days
  • D. 8 days

Explanation: The first group represents 10 × (6m + 8w) man-woman units, while the second represents 2 × (26m + 48w); equating them gives 60m + 80w =…

Correct answer: 4 days
  • A. 10 min
  • B. 20 min
  • C. 30 min
  • D. 40 min

Explanation: The two inlet taps fill at 1/12 + 1/15 = 3/20 cistern per minute, while the net rate with the outlet open is 1/20 cistern per minute.

Correct answer: 10 min
  • A. 5 min
  • B. 10 min
  • C. 15 min
  • D. 20 min

Explanation: The combined filling rate is 1/20 + 1/15 + 1/12 = 3/60 + 4/60 + 5/60 = 12/60 = 1/5 cistern per minute.

Correct answer: 5 min