A can do piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?
Correct answer: B. 120/7 days
- A. 70 days
- B. 120/7 days
- C. 50 days
- D. 45 days
Explanation
A's rate is 1/30 work per day and B's rate is 1/40 work per day, so together their rate is 1/30 + 1/40 = 7/120 work per day. Therefore, time = 1 ÷ (7/120) = 120/7 days. The likely trap is 70 days, from adding the individual times instead of their rates.
Last updated
About Time and Work
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Practise Arithmetic
1,060 free Arithmetic MCQs from Mathematics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Mathematics questions like this
Mathematics is on 67 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
Related questions
15 men can build a 500m long wall in 30 days. In how many days can 30 men build a 1.2 km long wall?
2 men and 12 women can finish a job in 4 days. 4 men and 6 women can do the same job in 5 days. Find the time taken by 1 man and 1 woman to complete the job.
3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in_______days.