Two pipes P and Q can fill a cistern in 12 minutes and 16 minutes respectively. Simultaneously both the pipes are opened together, then after how much time Q should be closed so that the tank is full in 9 min ?
Correct answer: C. 4 min
- A. 2 min
- B. 3 min
- C. 4 min
- D. 5 min
Explanation
If Q is closed after t minutes, P works for all 9 minutes and Q works for t minutes. The filled fraction is 9/12 + t/16 = 1, so 3/4 + t/16 = 1 and t/16 = 1/4, giving t = 4 minutes. The likely mistake is 3 minutes, which does not provide enough contribution from Q to complete the remaining quarter of the tank.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
About Time and Work
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Practise Arithmetic
1,060 free Arithmetic MCQs from Mathematics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Mathematics questions like this
Mathematics is on 76 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Time and Work questions
P, Q and R can complete a work in 24, 6 and 12 days respectively. The work will be completed in________days if all of them are working together.
If 10 bulls can plough 20 identical fields in 3 days working 10 hours a day, then in how many days can 30 bulls plough 32 same identical fields working 8 hours a day?
A can lay a railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in_________?
A can do a certain job in 12 days. B is 60% more efficient than A. The number of days it takes for B to do the same piece of work, is:_________?
A can do piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?
A and B can do a piece of work in 21 and 24 days respectively.They start the work together and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave?