  • A. 10 days
  • B. 12 days
  • C. 8 days
  • D. 9 days

Explanation: C completes half the work in 6 days, so C's rate is 1/12 of the work per day; in 4 days C completes 4/12 = 1/3 of the work, leaving 2/3.

Correct answer: 10 days
  • A. Rs.40
  • B. Rs.70
  • C. Rs.90
  • D. Rs.100

Explanation: Let the daily earnings of P, Q and R be p, q and r rupees per day. From the data, p + q + r = Rs.1620 ÷ 9 days = Rs.180 per day, p + r =…

Correct answer: Rs.70
  • A. 5 days
  • B. 10 days
  • C. 15 days
  • D. 12 days

Explanation: P's rate is 1/20 of the work per day and Q's rate is 1/12 of the work per day.

Correct answer: 10 days
  • A. 8
  • B. 6
  • C. 4
  • D. 2

Explanation: Q completes 10 days x 1/15 of the work per day = 2/3 of the work, leaving 1/3.

Correct answer: 6
  • A. 9(3/5) days
  • B. 9(1/5) days
  • C. 9(2/5) days
  • D. 10 days

Explanation: P, Q and R together work at 1/4 of the track per day, while P and Q together work at 1/16 + 1/12 = 7/48 of the track per day.

Correct answer: 9(3/5) days
  • A. 12 hrs
  • B. 14 hrs
  • C. 16 hrs
  • D. 18 hrs

Explanation: The combined filling rate of X and Y is 1/15 + 1/20 = 7/60 of the tank per hour, and Z empties 1/25 of the tank per hour, giving an…

Correct answer: 12 hrs
  • A. 12 days
  • B. 16 days
  • C. 18 days
  • D. 20 days

Explanation: If 1 man works 1.5 times as much as 1 boy, then 1 boy equals 2/3 of a man's daily work.

Correct answer: 16 days
  • A. 85 days
  • B. 126 days
  • C. 118 days
  • D. 136 days

Explanation: Efficiency and time are inversely proportional, so Rashid's and Danish's times are in the ratio 8:5 when their efficiencies are 5:8.

Correct answer: 136 days
  • A. 16
  • B. 4
  • C. 12
  • D. 8

Explanation: The total work is 12 men x 8 hours per day x 10 days = 960 man-hours. At 12 hours per day for 5 days, each man supplies 60 hours, so the…

Correct answer: 16
  • A. 15
  • B. 14
  • C. 16
  • D. 13

Explanation: Forty women working for 30 days provide 40 x 30 = 1,200 woman-days, so a woman's wage is Rs.21,600 ÷ 1,200 woman-days = Rs.18 per day.

Correct answer: 16
  • A. 7 hour 15 minutes
  • B. 7 hour 30 minutes
  • C. 8 hour 15 minutes
  • D. 8 hour 30 minutes

Explanation: Mansoor types 32 pages ÷ 6 hours = 16/3 pages per hour, while Aaqib types 40 pages ÷ 5 hours = 8 pages per hour.

Correct answer: 8 hour 15 minutes
  • A. 8/15
  • B. 7/15
  • C. 11/15
  • D. 2/11

Explanation: Their combined rate is 1/15 + 1/20 = 7/60 of the work per day. In 4 days they complete 4 x 7/60 = 7/15 of the work, so the fraction left…

Correct answer: 8/15
  • A. 40 days
  • B. 50 days
  • C. 60 days
  • D. 70 days

Explanation: A and B together complete 1/15 of the work per day, while B alone completes 1/20 per day.

Correct answer: 60 days
  • A. 50
  • B. 75
  • C. 60
  • D. 45

Explanation: Together they complete 20 days x 1/30 of the work per day = 2/3, leaving 1/3 for Kashif.

Correct answer: 50
  • A. 12:00 pm
  • B. 2:00 am
  • C. 12:00 am
  • D. 10:00 pm

Explanation: Jameel works from 9:00 am to 2:00 pm, which is 5 hours, and completes 5 hours x 1/15 of the work per hour = 1/3 of the work.

Correct answer: 12:00 am
  • A. 10
  • B. 9
  • C. 11
  • D. 12

Explanation: Q and R together work at 1/9 + 1/12 = 7/36 of the task per day, so in 3 days they complete 3 x 7/36 = 7/12, leaving 5/12.

Correct answer: 10
  • A. 14
  • B. 16
  • C. 15
  • D. 11

Explanation: Kamal's rate is 1/20 of the work per day. Suresh is 25% more efficient, so his rate is 1.25 x 1/20 = 1/16 work per day, meaning he needs…

Correct answer: 16
  • A. 37 ½ days
  • B. 22 days
  • C. 31 days
  • D. 22 days

Explanation: A completes 80% in 20 days, so A's rate is 0.8/20 = 0.04 = 1/25 work per day.

Correct answer: 37 ½ days
  • A. 75/8 days
  • B. 44/6 days
  • C. 48/5 days
  • D. None of these

Explanation: A's rate is (1/3) / 5 = 1/15 work per day, and B's rate is (2/5) / 10 = 1/25 work per day.

Correct answer: 75/8 days