A cistern has two taps which fill it in 12 min. and 15 min.respectively There is one outlet pipe in the cistern. When all the taps & pipe are opened, the empty cistern is full in 20 min. How long will the waste pipe (outlet) take to empty the full cistern ?
Correct answer: A. 10 min
- A. 10 min
- B. 20 min
- C. 30 min
- D. 40 min
Explanation
The two inlet taps fill at 1/12 + 1/15 = 3/20 cistern per minute, while the net rate with the outlet open is 1/20 cistern per minute. Thus the outlet rate is 3/20 - 1/20 = 1/10 cistern per minute, so it empties the cistern in 10 minutes. The likely mistake is 20 minutes, which treats the net filling time as the outlet's emptying time.
Last updated
About Time and Work
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Practise Arithmetic
1,060 free Arithmetic MCQs from Mathematics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Mathematics questions like this
Mathematics is on 67 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
Related questions
15 men can build a 500m long wall in 30 days. In how many days can 30 men build a 1.2 km long wall?
2 men and 12 women can finish a job in 4 days. 4 men and 6 women can do the same job in 5 days. Find the time taken by 1 man and 1 woman to complete the job.
3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in_______days.