All Free Mathematics MCQs with Answers

Every Mathematics question in the bank, across all chapters, each with the correct answer and a written explanation. Free and unlimited, with no account needed.

1,551 questions · page 62 of 78

  • A. 35 Rs.
  • B. 40 Rs.
  • C. 45 Rs.
  • D. None of these

Explanation: A and B have rates 1/10 and 1/15 work per day, whose ratio is 3:2, so A deserves 3/5 of the wages. A's share is (3/5) × Rs.75 = Rs.45.

Correct answer: 45 Rs.
  • A. 30 days
  • B. 25 days
  • C. 24 days
  • D. 20 days

Explanation: Equalising the total work gives 4(2m + 12w) = 5(4m + 6w), so 8m + 48w = 20m + 30w and m = 3w/2.

Correct answer: 24 days
  • A. 3/5
  • B. 4/7
  • C. 2/5
  • D. 1/4

Explanation: Their combined rate is 1/15 + 1/12 = 3/20 work per day, so in 4 days they complete 4 × 3/20 = 3/5 of the work.

Correct answer: 2/5
  • A. 48
  • B. 34(2/7)
  • C. 44
  • D. 45

Explanation: Using pairwise rates, 2A = (A+B) + (A+C) - (B+C) = 1/20 + 1/40 - 1/30 = 1/24 work per day, so A's rate is 1/48 work per day.

Correct answer: 48
  • A. 10
  • B. 8
  • C. 18
  • D. 19

Explanation: The rate of all three together is [(1/30) + (1/24) + (1/20)] ÷ 2 = 1/16 work per day, so in 10 days they complete 5/8 and leave 3/8.

Correct answer: 18
  • A. 5 5⁄11
  • B. 4 5⁄11
  • C. 6 4⁄11
  • D. 6 5⁄11

Explanation: A completes 12 days × 8 hours = 96 hours of work, so A's hourly rate is 1/96 work per hour; B's is 1/(8 × 10) = 1/80 work per hour.

Correct answer: 5 5⁄11
  • A. Rs. 380
  • B. Rs. 600
  • C. Rs. 420
  • D. Rs. 400Educational Resources

Explanation: A and B together work at 1/6 + 1/8 = 7/24 of the job per day, so in 3 days they complete 21/24 = 7/8 and C completes the remaining 1/8.

Correct answer: Rs. 400Educational Resources
  • A. 5 hrs
  • B. 10 hrs
  • C. 15 hrs
  • D. 20 hrs

Explanation: Let the slower pipe take t hours, so the faster takes t - 5 hours. Since together they fill 1/6 cistern per hour, 1/t + 1/(t - 5) = 1/6…

Correct answer: 15 hrs
  • A. 7.5 hrs
  • B. 5 hrs
  • C. 7 hrs
  • D. None of these

Explanation: The net rate is 1/10 + 1/12 - 1/20 = 6/60 + 5/60 - 3/60 = 8/60 = 2/15 tank per hour.

Correct answer: 7.5 hrs
  • A. 42/4 days
  • B. 41/4 days
  • C. 55 days
  • D. None of these

Explanation: In each two-day cycle, A and B complete 1/9 + 1/12 = 7/36 of the work. After four cycles, 28/36 = 7/9 is complete; A then works on day 9…

Correct answer: 41/4 days
  • A. 15 days
  • B. 10 days
  • C. 8 days
  • D. 20 days

Explanation: The complete work rate of 4 men and 2 women is 1/2 work per day. Two men complete 1/5 work per day, so 4 men complete 2/5 work per day…

Correct answer: 10 days
  • A. 32 hours
  • B. 48 hours
  • C. 3 days
  • D. 4 days

Explanation: If A works at x work per day, B works at 3x work per day, so together they work at 4x = 1 work per day.

Correct answer: 32 hours
  • A. 4(2/3) days
  • B. 4 days
  • C. 5(1/3) days
  • D. 1(1/3) days

Explanation: The three pair rates are 1/6, 1/12 and 1/8 work per day. Their sum is 3/8 work per day, which counts each person's rate twice, so the…

Correct answer: 5(1/3) days
  • A. 6 days
  • B. 10 days
  • C. 15 days
  • D. 20 days

Explanation: X completes 4 x 1/20 = 1/5 of the work in the first 4 days, leaving 4/5 of the work.

Correct answer: 10 days
  • A. 3 : 4
  • B. 4 : 3
  • C. 5 : 3
  • D. Data inadequate

Explanation: The same work equals 20 women x 16 days = 320 woman-days and 16 men x 15 days = 240 man-days.

Correct answer: 4 : 3
  • A. 80 days
  • B. 100 days
  • C. 120 days
  • D. 150 days

Explanation: Using pair rates, A's rate is (AB + AC - BC)/2 = (1/72 + 1/90 - 1/120)/2 = (1/60)/2 = 1/120 work per day.

Correct answer: 120 days
  • A. 8 days
  • B. 10 days
  • C. 12 days
  • D. 15 days

Explanation: Together A and B complete 1/15 + 1/10 = 1/6 work per day, so in 2 days they complete 1/3 of the work.

Correct answer: 12 days
  • A. 15 days
  • B. 20 days
  • C. 25 days
  • D. 30 days

Explanation: The condition says A's rate equals B plus C's rate. Since A and B together work at 1/10 work per day and C works at 1/50 work per day…

Correct answer: 25 days
  • A. 160
  • B. 175
  • C. 180
  • D. 195

Explanation: A regular four-week schedule has 5 x 8 x 4 = 160 regular hours, earning 160 x Rs. 2.40 = Rs. 384. The remaining Rs. 432 - Rs. 384 = Rs.

Correct answer: 175
  • A. 3
  • B. 4
  • C. 5
  • D. 6

Explanation: The loss in wages equals the number of absent days multiplied by the daily wage: Rs. 4956 - Rs. 3894 = Rs. 1062. The daily wage is Rs.

Correct answer: 3