Free Arithmetic MCQs with Answers
1,060 Arithmetic MCQs from Mathematics, each with the correct answer and a written explanation of why it is correct. Free and unlimited, with no account needed.
Arithmetic applies numerical operations to percentages, ratios, proportions, profit and loss, averages, and practical rate problems. Questions also involve time, speed and distance, and time and work, requiring careful use of units, direct and inverse relationships, weighted values, and work-rate methods rather than algebraic manipulation.
Last updated
1,060 questions · page 44 of 53
- A. 7
- B. 8
- C. 9
- D. 10
Explanation: The rates of P+Q, Q+R, and P+Q+R are 1/8, 1/12, and 1/6 work per day. Q's rate is 1/8 + 1/12 - 1/6 = 1/24, so P+R's rate is 1/6 - 1/24 =…
Correct answer: 8- A. 30 days
- B. 25 days
- C. 20 days
- D. 15 days
Explanation: Let Q's rate be q and R's rate be 1/50. Since P can do the work in the same time as Q and R together, P's rate is q + 1/50.
Correct answer: 25 days- A. 5,750 litres
- B. 5,760 litres
- C. 6,890 litres
- D. None of these
Explanation: Let the tank capacity be V litres. The leak removes V/6 litres per hour, while the inlet supplies 4 litres per minute = 240 litres per…
Correct answer: 5,760 litres- A. 12 min
- B. 14 min
- C. 16 min
- D. 20 min
Explanation: The filling rate is 1/32 tank per minute and the emptying rate is 1/16 tank per minute, so the net rate is 1/32 - 2/32 = -1/32 tank per…
Correct answer: 16 min- A. 20 days
- B. 30 days
- C. 40 days
- D. none of these
Explanation: The pair rates are A+B = 1/12, B+C = 1/15, and C+A = 1/20. Adding them gives 2(A+B+C) = 1/12 + 1/15 + 1/20 = 1/5, so the total rate is…
Correct answer: 30 days- A. 4
- B. 9.6
- C. 9
- D. 10
Explanation: A's rate is 1/16 and B's rate is 1/12, so their combined rate is 7/48 work per day.
Correct answer: 9.6- A. 2
- B. 8
- C. 10
- D. 12
Explanation: The original labour is 10 bulls x 3 days x 10 hours = 300 bull-hours for 20 fields, or 15 bull-hours per field.
Correct answer: 2- A. 2
- B. 3 3⁄7
- C. 4 ¼
- D. 5Election Officer Mcqs
Explanation: Their combined daily rate is 1/24 + 1/6 + 1/12 = 1/24 + 4/24 + 2/24 = 7/24 work per day.
Correct answer: 3 3⁄7- A. 2 min
- B. 3 min
- C. 4 min
- D. 5 min
Explanation: If Q is closed after t minutes, P works for all 9 minutes and Q works for t minutes.
Correct answer: 4 min- A. 12/6 days
- B. 15/2 days
- C. 23 days
- D. 34 days
Explanation: A's rate is 1/12 work per day. B is 60% more efficient, so B's rate is 1.6 x 1/12 = 1/7.5 work per day, and B's time is 12/1.6 = 7.5 days…
Correct answer: 15/2 days- A. 70 days
- B. 120/7 days
- C. 50 days
- D. 45 days
Explanation: A's rate is 1/30 work per day and B's rate is 1/40 work per day, so together their rate is 1/30 + 1/40 = 7/120 work per day.
Correct answer: 120/7 days- A. 5
- B. 6
- C. 7
- D. 8
Explanation: B completes 9/24 = 3/8 of the work in 9 days, so A and B together complete 5/8 of the work.
Correct answer: 7- A. 13
- B. 11
- C. 12
- D. 15
Explanation: A completes 2 × 1/8 = 1/4 of the work, leaving 3/4; B then completes 2/3 × 3/4 = 1/2, leaving 1/4.
Correct answer: 13- A. 20
- B. 25
- C. 125
- D. 60
Explanation: The number of tasks is proportional to the number of men and working hours, so tasks = 50 × (10 men × 6 hours) ÷ (6 men × 4 hours) = 125…
Correct answer: 125- A. 1
- B. 2
- C. 3
- D. 4
Explanation: Q's rate is 1/12 work per day, and P works twice as fast, so P's rate is 2/12 = 1/6 work per day.
Correct answer: 4- A. 9
- B. 11
- C. 23
- D. 13
Explanation: P's rate is 1/23 work per day; since P is 30% more efficient, Q's rate is 1/1.3 of P's rate = 10/299 work per day.
Correct answer: 13- A. 4 days
- B. 6 days
- C. 2 days
- D. 8 days
Explanation: The first group represents 10 × (6m + 8w) man-woman units, while the second represents 2 × (26m + 48w); equating them gives 60m + 80w =…
Correct answer: 4 days- A. 10 min
- B. 20 min
- C. 30 min
- D. 40 min
Explanation: The two inlet taps fill at 1/12 + 1/15 = 3/20 cistern per minute, while the net rate with the outlet open is 1/20 cistern per minute.
Correct answer: 10 min- A. 5 min
- B. 10 min
- C. 15 min
- D. 20 min
Explanation: The combined filling rate is 1/20 + 1/15 + 1/12 = 3/60 + 4/60 + 5/60 = 12/60 = 1/5 cistern per minute.
Correct answer: 5 min- A. 35 Rs.
- B. 40 Rs.
- C. 45 Rs.
- D. None of these
Explanation: A and B have rates 1/10 and 1/15 work per day, whose ratio is 3:2, so A deserves 3/5 of the wages. A's share is (3/5) × Rs.75 = Rs.45.
Correct answer: 45 Rs.