All Free Civil Engineering MCQs with Answers
Every Civil Engineering question in the bank, across all chapters, each with the correct answer and a written explanation. Free and unlimited, with no account needed.
631 questions · page 8 of 32
- A. An allowance for work not sufficiently defined at tender stage
- B. A fixed payment for work already completed on site
- C. A deduction made for defective materials after inspection
- D. An advance paid to the contractor before mobilisation
Explanation: A provisional sum is an allowance for work whose scope or quantity cannot be defined accurately when tenders are invited.
Correct answer: An allowance for work not sufficiently defined at tender stage- A. To record the daily output of reinforcement workers
- B. To list reinforcement bar sizes, shapes, lengths, and quantities
- C. To show the planned sequence of concrete placement activities
- D. To calculate the electrical load of a reinforced concrete building
Explanation: A bar bending schedule provides the information needed to cut, bend, identify, and place reinforcement bars.
Correct answer: To list reinforcement bar sizes, shapes, lengths, and quantities- A. The horizontal distance for transporting excavated soil
- B. The volume of soil compacted in one working layer
- C. The vertical distance through which excavated soil is moved
- D. The number of passes made by a compaction roller
Explanation: Lift is the vertical distance through which excavated or deposited material is moved.
Correct answer: The vertical distance through which excavated soil is moved- A. To certify the final quality of completed construction work
- B. To record the names of workers assigned to each activity
- C. To show the sequence in which project activities are completed
- D. To list agreed unit rates for commonly measured work items
Explanation: A schedule of rates contains unit prices for specified work items and can support valuation or pricing where final quantities are not…
Correct answer: To list agreed unit rates for commonly measured work items- A. When varied work cannot be priced reliably from existing rates
- B. When the whole project is awarded for one fixed lump sum
- C. When the contractor has completed all work before payment begins
- D. When only the employer's permanent staff perform the work
Explanation: Daywork is used for instructed work whose quantities or nature make normal unit-rate pricing impractical.
Correct answer: When varied work cannot be priced reliably from existing rates- A. The contractor's confidential calculation of expected profit
- B. The employer's estimate used to assess the reasonableness of bids
- C. The final amount certified after all construction defects are corrected
- D. The total value of materials purchased by the contractor
Explanation: An engineer's estimate is prepared for the employer before or during tendering to indicate the expected project cost and help evaluate…
Correct answer: The employer's estimate used to assess the reasonableness of bids147. Which document most directly shows the condition and layout of a completed construction project?
- A. The original feasibility report
- B. The contractor's tender programme
- C. The approved as-built drawings
- D. The preliminary abstract of cost
Explanation: As-built drawings record the work as actually constructed, including approved changes from the original design.
Correct answer: The approved as-built drawings- A. To replace all training and supervision of site workers
- B. To calculate the quantities of materials used on site
- C. To approve the contractor's monthly payment certificate
- D. To authorise and control specified high-risk activities
Explanation: A permit-to-work system formally authorises hazardous activities after required precautions, isolations, and responsibilities are…
Correct answer: To authorise and control specified high-risk activities- A. The difference between discounted benefits and discounted costs
- B. The difference between planned and actual quantities of concrete
- C. The percentage of project work completed at a given date
- D. The total number of resources assigned to a project activity
Explanation: Net present value discounts future project cash inflows and outflows to the present and calculates their net difference.
Correct answer: The difference between discounted benefits and discounted costs- A. To increase the measured dimensions of the completed structure
- B. To account for unavoidable losses during handling and installation
- C. To replace the contractor's obligation to store materials safely
- D. To include the employer's land acquisition and design expenses
Explanation: A reasonable wastage allowance covers losses caused by cutting, breakage, spillage, or handling during construction.
Correct answer: To account for unavoidable losses during handling and installation- A. Number of rooms in the building
- B. Total height of the proposed building
- C. Current cost per unit of plinth area
- D. Average wall thickness of the building
Explanation: The plinth area method uses a known or assessed rate per unit area, such as cost per square metre.
Correct answer: Current cost per unit of plinth area- A. The site has passed the safety inspection
- B. The contractor has submitted the lowest tender
- C. The project has received its final payment
- D. The design and detailed estimate are technically adequate
Explanation: Technical sanction is approval of the detailed design, specifications, quantities and estimated cost by the competent technical authority.
Correct answer: The design and detailed estimate are technically adequate- A. Placing an order and receiving the required item
- B. Starting excavation and completing the foundation
- C. Submitting a tender and opening the bids
- D. Measuring completed work and making payment
Explanation: Lead time covers the waiting period from placing an order until the material, equipment or service becomes available for use.
Correct answer: Placing an order and receiving the required item- A. To replace the contract drawings and specifications
- B. To document decisions, responsibilities and agreed actions
- C. To calculate the exact quantity of every completed item
- D. To authorize payment without measurement or certification
Explanation: Meeting minutes create a formal record of decisions, assigned responsibilities, deadlines and unresolved issues.
Correct answer: To document decisions, responsibilities and agreed actions- A. The contractor's profit multiplied by project duration
- B. A single fixed price for the complete project
- C. Recorded labour time plus the cost of materials used
- D. The lowest price submitted by competing contractors
Explanation: A time-and-materials contract pays for verified labour hours and materials, usually with an agreed markup or fee.
Correct answer: Recorded labour time plus the cost of materials used- A. The contractor's legal claims against the employer
- B. Only the names of responsible site supervisors
- C. Only the physical dimensions of completed work
- D. Budgeted cost values linked to planned work
Explanation: A cost-loaded schedule links planned activity costs with dates and quantities of work.
Correct answer: Budgeted cost values linked to planned work- A. The value recovered from an asset at the end of its useful life
- B. The original purchase price of an asset before construction
- C. The annual rent received from an occupied property
- D. The cost of repairing an asset after ordinary maintenance
Explanation: Salvage value is the estimated amount recoverable when an asset is retired, sold or dismantled.
Correct answer: The value recovered from an asset at the end of its useful life- A. Current market rent of the property
- B. Estimated useful life of the asset
- C. Original construction area of the asset
- D. Number of occupants using the asset
Explanation: Straight-line depreciation spreads depreciable cost evenly over the estimated useful life.
Correct answer: Estimated useful life of the asset- A. To determine the legal ownership of the completed building
- B. To record the contractor's daily attendance at the site
- C. To coordinate when materials, equipment and services are required
- D. To replace the approved construction method statement
Explanation: A procurement schedule identifies required items, ordering dates, delivery dates and responsible parties.
Correct answer: To coordinate when materials, equipment and services are required- A. Delay damages payable for late completion
- B. Unforeseen excavation work with no defined scope
- C. The contractor's fixed annual office overhead
- D. A specified supply item whose final selection or price is unsettled
Explanation: A prime cost sum is an allowance for a particular item, commonly supplied by a nominated or selected supplier, when its exact cost is not…
Correct answer: A specified supply item whose final selection or price is unsettled