What is the main purpose of recording minutes of a construction site meeting?
Correct answer: B. To document decisions, responsibilities and agreed actions
- A. To replace the contract drawings and specifications
- B. To document decisions, responsibilities and agreed actions
- C. To calculate the exact quantity of every completed item
- D. To authorize payment without measurement or certification
Explanation
Meeting minutes create a formal record of decisions, assigned responsibilities, deadlines and unresolved issues. They support coordination and accountability but do not replace contract documents or payment certification.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
In construction procurement, lead time is the period between:
In public works administration, technical sanction primarily confirms that:
In a preliminary building estimate, the plinth area method calculates cost mainly by multiplying the plinth area by the:
Under a time-and-materials construction contract, payment is generally based on:
What does a cost-loaded construction schedule assign to project activities?
In property valuation, what does salvage value mean?