What does a cost-loaded construction schedule assign to project activities?

Correct answer: D. Budgeted cost values linked to planned work

  • A. The contractor's legal claims against the employer
  • B. Only the names of responsible site supervisors
  • C. Only the physical dimensions of completed work
  • D. Budgeted cost values linked to planned work

Explanation

A cost-loaded schedule links planned activity costs with dates and quantities of work. This allows planned expenditure to be compared with actual cost and progress during project control.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions