In a preliminary building estimate, the plinth area method calculates cost mainly by multiplying the plinth area by the:

Correct answer: C. Current cost per unit of plinth area

  • A. Number of rooms in the building
  • B. Total height of the proposed building
  • C. Current cost per unit of plinth area
  • D. Average wall thickness of the building

Explanation

The plinth area method uses a known or assessed rate per unit area, such as cost per square metre. The other factors may affect cost but do not directly form the basic calculation in this method.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions