What is an engineer's estimate in a construction tendering process?

Correct answer: B. The employer's estimate used to assess the reasonableness of bids

  • A. The contractor's confidential calculation of expected profit
  • B. The employer's estimate used to assess the reasonableness of bids
  • C. The final amount certified after all construction defects are corrected
  • D. The total value of materials purchased by the contractor

Explanation

An engineer's estimate is prepared for the employer before or during tendering to indicate the expected project cost and help evaluate submitted bids. It is not the contractor's internal profit calculation or the final account.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions