What is the primary purpose of a bar bending schedule in construction documentation?
Correct answer: B. To list reinforcement bar sizes, shapes, lengths, and quantities
- A. To record the daily output of reinforcement workers
- B. To list reinforcement bar sizes, shapes, lengths, and quantities
- C. To show the planned sequence of concrete placement activities
- D. To calculate the electrical load of a reinforced concrete building
Explanation
A bar bending schedule provides the information needed to cut, bend, identify, and place reinforcement bars. It is not a programme for reinforcement work or a record of labour productivity.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
In a bill of quantities, what does a provisional sum normally represent?
When estimating equipment operating cost, which item is most directly related to the machine's actual running time?
In traditional design-bid-build procurement, which party normally completes the design before construction tendering?
In earthwork measurement, what does the term lift refer to?
What is the main purpose of a schedule of rates in construction procurement?
When is daywork measurement most appropriately used in construction payment?