Which risks are associated with constraints imposed by management or the marketplace ?

Correct answer: A. Business impact risks

  • A. Business impact risks
  • B. Process definition risks
  • C. Product size risks
  • D. Development environment risks

Explanation

Business impact risks result from management decisions, market conditions, or business constraints that affect the project. The other categories concern processes, product size, or the technical development environment.