Which of the following term is best defined by the statement:"the degree of uncertainty that the product will meet its requirements and be fit for its intended use."?
Correct answer: A. Performance risk
- A. Performance risk
- B. Cost risk
- C. Support risk
- D. Schedule risk
Explanation
Performance risk measures uncertainty about whether the product will satisfy its requirements and intended use. Cost and schedule risks concern expenditure and completion time, not product fitness.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which of the following risk is the failure of a purchased component to perform as expected ?
Which of the following risks are derived from the software or hardware technologies that are used to develop the system ?
Which of the following strategies means that the impact of the risk will be reduced ?
Which of the following term is best defined by the statement: "There will be a change of organizational management with different priorities."?
Which risks are associated with constraints imposed by management or the marketplace ?
What threatens the quality and timeliness of the software to be produced ?