Which of the following term is best defined by the statement:"the degree of uncertainty that the product will meet its requirements and be fit for its intended use."?
Correct answer: A. Performance risk
- A. Performance risk
- B. Cost risk
- C. Support risk
- D. Schedule risk
Explanation
Performance risk measures uncertainty about whether the product will satisfy its requirements and intended use. Cost and schedule risks concern expenditure and completion time, not product fitness.
Last updated
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
A __________ is a measure, an intangible measure, which is difficult to count in clear terms?
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A listing of the names and addresses of all the employees for an organization would be an example of a(n)_________________________?
A make-buy decision is based on whether________________?