Which of the following term is best defined by the statement:"the degree of uncertainty that the product will meet its requirements and be fit for its intended use."?

Correct answer: A. Performance risk

  • A. Performance risk
  • B. Cost risk
  • C. Support risk
  • D. Schedule risk

Explanation

Performance risk measures uncertainty about whether the product will satisfy its requirements and intended use. Cost and schedule risks concern expenditure and completion time, not product fitness.