Moderate

Which of the following risks are derived from the software or hardware technologies that are used to develop the system ?

Correct answer: B. Technology risks

  • A. Managerial risks
  • B. Technology risks
  • C. Estimation risks
  • D. Organizational risks

Explanation

Technology risks arise from the software, hardware, tools, or platforms used to develop and operate the system. Managerial and organizational risks instead concern people, processes, and institutions.

Last updated

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.