Which software project sizing approach develop estimates of the information domain characteristics ?

Correct answer: A. Function point sizing

  • A. Function point sizing
  • B. Change sizing
  • C. Standard component sizing
  • D. Fuzzy logic sizing

Explanation

Function point sizing estimates the software’s information-domain characteristics, such as inputs, outputs, inquiries, files, and interfaces. The other listed methods do not specifically perform this standard information-domain measurement.