If a Direct approach to software project sizing is taken, size can be measured in__________________?
Correct answer: A. LOC
- A. LOC
- B. FP
- C. LOC and FP
- D. None of the mentioned
Explanation
A direct sizing approach measures a tangible implementation quantity, most commonly Lines of Code (LOC). Function Points are associated with indirect, functionality-based sizing.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
The expected value for the estimation variable (size), S, can be computed as a weighted average of the optimistic(Sopt), most likely (Sm), and pessimistic (Spess) estimates given as___________________?
If an Indirect approach is taken, then the sizing approach is represented as_______________?
Which of the following is not an effective software project management focus ?
How many forms exists of Barry Boehm's COCOMO Model ?
Which software project sizing approach develop estimates of the information domain characteristics ?
Why is decomposition technique required ?