If an Indirect approach is taken, then the sizing approach is represented as_______________?
Correct answer: B. FP
- A. LOC
- B. FP
- C. Fuzzy Logic
- D. LOC and FP
Explanation
An indirect sizing approach measures software size through functionality, commonly using Function Points (FP). A direct approach generally counts implementation size such as Lines of Code (LOC).
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which of the following is not an effective software project management focus ?
Which of the following is not an approach to software cost estimation ?
Which of the following is not an effective project manager trait ?
The expected value for the estimation variable (size), S, can be computed as a weighted average of the optimistic(Sopt), most likely (Sm), and pessimistic (Spess) estimates given as___________________?
If a Direct approach to software project sizing is taken, size can be measured in__________________?
How many forms exists of Barry Boehm's COCOMO Model ?