Which of the following strategies means that the impact of the risk will be reduced ?

Correct answer: B. Minimization strategies

  • A. Avoidance strategies
  • B. Minimization strategies
  • C. Contingency plans
  • D. All of the mentioned

Explanation

Minimization strategies reduce the probability or impact of a risk while allowing the project to continue. Avoidance attempts to remove the risk entirely, whereas contingency plans specify what to do after a risk occurs.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions