Which of the following strategies means that the impact of the risk will be reduced ?
Correct answer: B. Minimization strategies
- A. Avoidance strategies
- B. Minimization strategies
- C. Contingency plans
- D. All of the mentioned
Explanation
Minimization strategies reduce the probability or impact of a risk while allowing the project to continue. Avoidance attempts to remove the risk entirely, whereas contingency plans specify what to do after a risk occurs.
Last updated
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
A __________ is a measure, an intangible measure, which is difficult to count in clear terms?
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A listing of the names and addresses of all the employees for an organization would be an example of a(n)_________________________?
A make-buy decision is based on whether________________?