Which of the following risk is the failure of a purchased component to perform as expected ?

Correct answer: A. Product risk

  • A. Product risk
  • B. Project risk
  • C. Business risk
  • D. Programming risk

Explanation

A purchased component that fails to perform as expected creates a product risk because it affects the capabilities or quality of the delivered system. Project risks primarily affect cost, schedule, or resources.