Which risks are associated with the overall size of the software to be built or modified ?
Correct answer: C. Product size risks
- A. Business impact risks
- B. Process definition risks
- C. Product size risks
- D. Development environment risks
Explanation
Product size risks are associated with the scale of the software being built or modified, including its scope, complexity, and amount of functionality. Business impact and process-definition risks address different sources of uncertainty.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which of the following is not a business risk ?
What threatens the quality and timeliness of the software to be produced ?
Which risks are associated with constraints imposed by management or the marketplace ?
What threatens the viability of the software to be built ?
What is the product of the probability of incurring a loss due to the risk and the potential magnitude of that loss ?
COCOMO stands for____________________?