Which of the following is not a business risk ?
Correct answer: C. lack of documented requirements or software scope
- A. building an excellent product or system that no one really wants
- B. losing the support of senior management due to a change in focus or change in people
- C. lack of documented requirements or software scope
- D. losing budgetary or personnel commitment
Explanation
Lack of documented requirements or a clear software scope is a project or requirements-management problem, not a business risk. The other choices describe loss of market demand, management support, or project commitment.
Last updated
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
A __________ is a measure, an intangible measure, which is difficult to count in clear terms?
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A listing of the names and addresses of all the employees for an organization would be an example of a(n)_________________________?
A make-buy decision is based on whether________________?