Which of the following is not a business risk ?
Correct answer: C. lack of documented requirements or software scope
- A. building an excellent product or system that no one really wants
- B. losing the support of senior management due to a change in focus or change in people
- C. lack of documented requirements or software scope
- D. losing budgetary or personnel commitment
Explanation
Lack of documented requirements or a clear software scope is a project or requirements-management problem, not a business risk. The other choices describe loss of market demand, management support, or project commitment.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
What threatens the quality and timeliness of the software to be produced ?
Which risks are associated with constraints imposed by management or the marketplace ?
Which of the following term is best defined by the statement: "There will be a change of organizational management with different priorities."?
Which risks are associated with the overall size of the software to be built or modified ?
What threatens the viability of the software to be built ?
What is the product of the probability of incurring a loss due to the risk and the potential magnitude of that loss ?