Which technique is applicable when other projects in the same analogy application domain have been completed ?
Correct answer: C. Estimation by analogy
- A. Algorithmic cost modelling
- B. Expert judgement
- C. Estimation by analogy
- D. Parkinson's Law
Explanation
Estimation by analogy uses actual cost and effort data from completed projects that are similar in domain, size, and characteristics. It is especially useful when comparable historical projects exist.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which of the following states that work expands to fill the time available ?
Which model is used to compute the effort required to integrate reusable components or program code that is automatically generated by design or program translation tools ?
Which model is used during early stages of the system design after the requirements have been established ?
Which of the following costs is not part of the total effort cost ?
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
CLSS stands for_____________________?