Which technique is applicable when other projects in the same analogy application domain have been completed ?

Correct answer: C. Estimation by analogy

  • A. Algorithmic cost modelling
  • B. Expert judgement
  • C. Estimation by analogy
  • D. Parkinson's Law

Explanation

Estimation by analogy uses actual cost and effort data from completed projects that are similar in domain, size, and characteristics. It is especially useful when comparable historical projects exist.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions