Which technique is applicable when other projects in the same analogy application domain have been completed ?

Correct answer: C. Estimation by analogy

  • A. Algorithmic cost modelling
  • B. Expert judgement
  • C. Estimation by analogy
  • D. Parkinson's Law

Explanation

Estimation by analogy uses actual cost and effort data from completed projects that are similar in domain, size, and characteristics. It is especially useful when comparable historical projects exist.