Which of the following costs is not part of the total effort cost ?

Correct answer: C. Costs of lunch time food

  • A. Costs of networking and communications
  • B. Costs of providing heating and lighting office space
  • C. Costs of lunch time food
  • D. Costs of support staff

Explanation

Total effort cost includes items such as staff, support personnel, communications, and office facilities. Employees' lunchtime food is generally a personal expense rather than a project effort cost.