A _______________ is developed using historical cost information that relates some software metric to the project cost ?
Correct answer: A. Algorithmic cost modelling
- A. Algorithmic cost modelling
- B. Expert judgement
- C. Estimation by analogy
- D. Parkinson's Law
Explanation
Algorithmic cost modelling applies a formula derived from historical relationships between software metrics, such as size, and project cost. Expert judgement and analogy rely primarily on human comparison or experience rather than an explicit cost equation.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which of the following costs is not part of the total effort cost ?
Which technique is applicable when other projects in the same analogy application domain have been completed ?
Which of the following states that work expands to fill the time available ?
CLSS stands for_____________________?
The environment that supports the software project is called_______________________?
What is related to the overall functionality of the delivered software ?