Which of the following model has a major disadvantage in terms of the coding phase of a software life cycle model ?

Correct answer: D. 4GT Model

  • A. Spiral Model
  • B. Waterfall Model
  • C. Rad Model
  • D. 4GT Model

Explanation

The 4GT model reduces conventional coding through generators and high-level specifications, but its generated code can be difficult to control, optimize, and maintain. This makes the coding phase a significant limitation of the model.