Which of the following does not apply to agility to a software process ?
Correct answer: C. Eliminate the use of project planning and testing
- A. Uses incremental product delivery strategy
- B. Only essential work products are produced
- C. Eliminate the use of project planning and testing
- D. All of the mentioned
Explanation
Agile development still requires planning and testing, although both are performed iteratively and kept lightweight. Incremental delivery and producing only essential work products are consistent with agility.
Last updated
Practise Software Development Lifecycle
423 free Software Development Lifecycle MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
4GL is an example of ________________ processing?
A company is developing an advance version of their current software available in the market, what model approach would they prefer ?
A cross life-cycle activity of system development is____________________?
A development stategy whereby the executive control modules of a system are coded and tested first, is known as________________?
A disk's content that is recorded at the time of manufacture and that cannot be changed or erased by the user is__________________?