Which of the following does not apply to agility to a software process ?

Correct answer: C. Eliminate the use of project planning and testing

  • A. Uses incremental product delivery strategy
  • B. Only essential work products are produced
  • C. Eliminate the use of project planning and testing
  • D. All of the mentioned

Explanation

Agile development still requires planning and testing, although both are performed iteratively and kept lightweight. Incremental delivery and producing only essential work products are consistent with agility.