How is plan driven development different from agile development ?
Correct answer: C. Iteration occurs within activities
- A. Outputs are decided through a process of negotiation during the software development process
- B. Specification, design, implementation and testing are interleaved
- C. Iteration occurs within activities
- D. All of the mentioned
Explanation
In plan-driven development, iteration generally occurs within separate activities such as requirements, design, or testing, whereas agile development interleaves these activities. Agile development also negotiates outputs during development, so option c identifies the plan-driven distinction intended here.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Development Lifecycle
423 free Software Development Lifecycle MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Development Lifecycle questions
Which of the following does not apply to agility to a software process ?
Four types of change are encountered during the support phase . Which one of the following is not one that falls into such category ?
Which of the following activities of a Generic Process framework provides a feedback report ?
Agile Software Development is based on_________________?
Which of the following model has a major disadvantage in terms of the coding phase of a software life cycle model ?
Select the option that suits the Manifesto for Agile Software Development________________?