Which of the following is the task of project indicators ?

Correct answer: C. help in assessment of status of ongoing project & track potential risk

  • A. help in assessment of status of ongoing project
  • B. track potential risk
  • C. help in assessment of status of ongoing project & track potential risk
  • D. none of the mentioned

Explanation

Project indicators show the current status of an ongoing project and provide early warning of potential risks. Both functions are needed for effective project monitoring.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions