What is a tangible output of an activity that is predicted in a project plan ?

Correct answer: A. Deliverable

  • A. Deliverable
  • B. Activity
  • C. Condition
  • D. Process

Explanation

A deliverable is a tangible, verifiable output produced by completing a project activity, such as a report, prototype, or software release. An activity is the work itself, not its resulting output.