A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
Correct answer: C. Control Chart
- A. DRE (Defect Removal Efficiency)
- B. Function points analysis
- C. Control Chart
- D. All of the mentioned
Explanation
A control chart plots metric values over time against expected control limits, helping distinguish normal variation from meaningful change. DRE and function-point analysis serve different measurement purposes.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which of the following is an indirect measure of product ?
Which of the following does not affect the software quality and organizational performance ?
Which of the following is not a direct measure of SE process ?
In size oriented metrics, metrics are developed based on the _____________________?
The intent of project metrics is_____________________?
Which of the following is the task of project indicators ?